Siebel Upgrade from 7.8 to 8.1

1 In-Scope

• Setup of the Development Environment
• Changes to the User Interface, Scripts, and Data Models
• Validation of Workflows, which include Business Services
• Impact Analysis for all interfaces after the upgrade to Siebel 8.1.1. Only the Impact Analysis - Interfaces report will be prepared
• Unit Testing of the User Interface. This will include script validation
• Tracking and resolution of defects and issues
• Functionality testing for 500 test cases for the web client. Only existing test cases will be used
• Install OBI server and configure to Siebel 8.1.1 development upgrade environment
• Analysis of the vanilla Siebel 8.1.1 reports. Configure those that closely matches the existing Siebel 7.8 vanilla reports
• Configure all reports with minimal configuration in terms of additional labels changes and fields
• Prepare a report for all the customized/Complex reports that can not be configured before end of this project

2.2 Out of Scope

• End to end testing of all interfaces
• Development of any Interfaces integrated with Siebel 7.8 after upgrade to Siebel 8.1
• Setup and validation of interfaces (if required) for successful execution of test cases
• Development of the Customized/Complex BI reports which can not be configured before end of the project
• Test environment setup, system integration testing and UAT
• Remote user testing
• Performance testing